KILO · EVIDENCE ANNEX

The evidence supporting KILO.

A source-referenced companion to the Site Assessment.

A development-stage campus opportunity in Kerr County, Texas. This annex records the evidence, its limits and the diligence outputs needed for subsequent commitments.

12review domains
39recorded claims
12proposed actions

Editorial revision: September 16, 2026.
Retained analysis snapshot: September 15, 2026.

Use this annex to

  1. Locate a claim and its recorded document pages.
  2. Distinguish evidence from planning assumptions.
  3. Define the next diligence output and decision.

Original-document verification is outside this edition’s preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL01 / 31
KILO · EVIDENCE ANNEX

What this edition establishes

The retained analysis supports scoped diligence. It does not establish project readiness or a commercial commitment.

Preparation basis

This annex summarizes the retained Kilo source analysis and its recorded document and page references. Original-document verification is outside this edition’s preparation basis. Confirm the cited records against current originals before relying on them for a commercial commitment.

Source-record status

“Confirmed” and “Submitted” reproduce the source record’s classifications. They do not constitute this edition’s verification of original documents or completion of the underlying obligations.

Claim statements retain their recorded facts and statuses. Analyst notes and proposed actions are edited for clarity; the exact retained text remains in the evidence register.

Decision use

The record reports land-control documentation, utility development agreements and preliminary engineering. It provides a starting point for a phased tenant brief and a defined diligence scope.

Conditions still governing commitment

Firm power availability, sustainable water supply, binding fuel arrangements, resilient connectivity and a tenant ready-for-service date remain to be established.

Read the source types separately

Document references support recorded claims. Analyst synthesis explains implications. Proposed actions identify work still required. Historical platform scores and evidence counts use separate bases.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL02 / 31
KILO · EVIDENCE ANNEX

Find the evidence for the decision

Use domain links for claim-level detail and source links for original titles and recorded pages.

Key terms: BTM, behind the meter; OEM, original equipment manufacturer; EPC, engineering, procurement and construction; IRU, indefeasible right of use. LCRA, Lower Colorado River Authority; PEC, Pedernales Electric Cooperative; ERCOT, Electric Reliability Council of Texas; TCEQ, Texas Commission on Environmental Quality. VDR, virtual data room; POI, point of interconnection; FEA, Facility Extension Agreement.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL03 / 31
KILO · EVIDENCE ANNEX

Evidence coverage in the retained matrix

59 descriptive items across 12 domains; the 39 recorded claims use a different unit of analysis.

DomainCoveredPartialNot foundSource description
Grid interconnection430Completion gaps
Natural gas050Completion gaps
Land title330Completion gaps
Transmission / substation230Completion gaps
Environmental / geotech231Completion gaps
Water122Evidence gaps
Fiber130Completion gaps
Access / site plan031Evidence gaps
Equipment / procurement130Completion gaps
Schedule301Completion gaps
Appraisal / finance013Evidence gaps
Permitting014Evidence gaps
Total17301259 descriptive items

“Completion gaps” abbreviates the source description “Meaningful evidence but material completion gaps”. Counts are reproduced from the descriptive assessment. They are neither project-completion percentages nor a score. The retained records do not provide an item-level crosswalk from this matrix to the claim register. Descriptive assessment basis

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL04 / 31
KILO · EVIDENCE ANNEX

Resolve the service and transaction basis

Proposed diligence outputs · capacity, supply, title and schedule

Proposed outputEvidence requiredDecision informed
Establish the utility capacity and service basisComplete studies, approvals, upgrades, security, supply and energization authority for the requested 2,100 MW.Determine the capacity and service conditions available for a phased tenant brief.
Obtain binding fuel and transportation termsUpdate the source-described expired proposal; negotiate binding fuel and transportation terms and coordinate the lateral, plant, OEM, EPC, air permit and fuel balance.Assess whether the proposed generation phase has an executable fuel and plant basis.
Demonstrate the phased water supplyDrill and test priority targets, establish rights and permits, and complete the phased water and wastewater balance.Assess whether supply and treatment can support the proposed cooling design.
Contract and validate resilient connectivityObtain allocation and commercial terms, survey and secure the lateral, validate latency and document physical diversity.Define the connectivity service and delivery conditions available to a tenant.
Complete title and parcel reconciliationObtain current title exceptions and mineral review; reconcile deed, survey, Phase I, appraisal, tax and KML acreage.Define the land and corridor rights that can support a transaction.
Establish one governing delivery scheduleReconcile workstream dates and milestone definitions in a current baseline with dependencies, critical path and contingency.Identify which dates can be communicated and the conditions attached to each.

All outputs remain open. Agree owners, timing, scope and acceptance criteria; review completion evidence. This is not an agreed critical path.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL05 / 31
KILO · EVIDENCE ANNEX

Define the engineering and execution basis

Proposed diligence outputs · design, approvals, procurement and capital

Proposed outputEvidence requiredDecision informed
Complete the corridor and substation designSurvey the route, secure rights and crossing approval, reconcile endpoints and complete utility-approved design.Establish the route and design basis for construction planning.
Complete targeted field and design studiesInvestigate geotechnical/karst, wetlands/waters, flood/drainage and generation-related air/noise constraints.Determine which areas and facilities can advance into detailed design.
Issue the logistics and utility master planReconcile legal access; complete heavy-haul, emergency access, grading, drainage, stormwater and integrated corridor design.Coordinate the campus footprint, construction access and utility interfaces.
Confirm equipment commitmentsProvide unredacted vendor/EPC commitments, slots/payment evidence, final specifications, acceptance plans and logistics.Determine whether equipment availability supports the proposed construction sequence.
Create the permit register and confirm statusAdvance priority applications, retain agency correspondence and link each approval to design and schedule conditions.Identify the approvals and application status governing each development phase.
Reconcile valuation and capital planningUpdate valuation for title and infrastructure maturity; provide phased budget, capital plan, incentives, commitments and downside cases.Support an investment discussion on a consistent land, cost and funding basis.

All outputs remain open. Agree owners, timing, scope and acceptance criteria; review completion evidence. This is not an agreed critical path.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL06 / 31
KILO · EVIDENCE ANNEX

Source differences requiring reconciliation

Different scopes and versions remain separate until the governing evidence is established.

TopicDifferent recordsWording supported hereEvidence to resolve
Requested load and concept capacityRecorded utility study request: 2,100 MW. A separate platform record uses 2,000 MW and interconnection-agreement wording; the IT concept also shows 2,000 MW.Use 2,100 MW only as the requested study load at 345 kV. Keep the separate IT concept and platform wording distinct.Reconcile current utility originals and the IT design basis; identify the source and meaning of each value.
Generation schedulesAuthored preliminary Phase 1: 442 CAT G3520K engines / 1,105 MW. Separate Ascendant supporting schedule: 191 engines / 477.5 MW.Present as separate preliminary records; neither aggregation nor supersession is established.Obtain current schedules and identify scope, relationships, version authority and the governing baseline.
Gas commercial recordsMay 13 Kinder Morgan proposal, described as expired in the retained analysis. Separate May 7 Oasis summary of proposed terms and a nonbinding generation inference.Describe each as its own commercial record. Binding fuel and transportation terms remain to be negotiated.Obtain current proposals or agreements and reconcile counterparties, terms, delivery points and status.

Unresolved in retained analysis; owners and dates require agreement. No competing record is treated as superseded or incorrect. Detailed provenance is retained.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL07 / 31
KILO · EVIDENCE ANNEX

Source differences requiring reconciliation · continued

Different scopes and versions remain separate until the governing evidence is established.

TopicDifferent recordsWording supported hereEvidence to resolve
Land and assessment scopesSurvey: 3,979.63 acres. Deed: 3,980.63 gross acres less 1.00 acre. Phase I: 4,005.86 acres / 24 parcels. Appraisal: 4,500-acre premise.Keep each acreage’s scope label. Gross deed less the exception equals the survey; parcel reconciliation is still required.Prepare a parcel crosswalk tying deed, survey, title, appraisal, assessment, tax and KML records.
Milestone definitionsPreliminary first 40 MW BTM substantial completion: June 14, 2027. Grid-study target: April 1, 2028. Conditional PEC ramp: 600 / 1,200 / 2,100 MW by year-end 2030 / 2031 / 2032.Keep the milestones distinct. None establishes a reconciled tenant ready-for-service commitment.Agree milestone definitions and a current integrated schedule with dependencies and contingency.
Finance records and platform scoresThe authored analysis cites an appraisal. The stored finance score is 90; a separate domain display is 50 with an appraisal-not-found note.Use the appraisal with its scope and assumptions. Neither platform value establishes finance readiness.Reconcile the appraisal record and platform versions; document the basis and method before interpreting a score.

Unresolved in retained analysis; owners and dates require agreement. No competing record is treated as superseded or incorrect. Detailed provenance is retained.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL08 / 31
DOMAIN 01 · RECORDED EVIDENCE

Grid interconnection · evidence

A requested 2,100 MW study basis; firm capacity, electricity supply and energization remain to be established.

Status labels reproduce the source record. Preparation basis.

grid-03Confirmed

PEC and Blue Fox executed a Transmission Facility Extension Agreement effective July 10, 2026, with construction and service contingent on studies, approvals, security, access rights, and other prerequisites.

grid-04Submitted

ERCOT-format surveys identify LLI-2421 Kerr Data Center, a 345 kV interconnection, and a planned 2,100 MW load whose detailed design remains incomplete.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL09 / 31
DOMAIN 01 · IMPLICATIONS AND PROPOSED OUTPUT

Grid interconnection · decision

Executed development instruments define a requested 2,100 MW study basis; firm capacity, electric-energy supply and energization remain to be established.

Analyst implications

Complete the issued studies, ERCOT and utility approvals, final upgrade scope, security and energization authority required to establish firm capacity.

Arrange electric-energy supply separately: the PEC facility agreement does not itself supply power.

Proposed next output

Establish the utility capacity and service basis

Complete studies, approvals, upgrades, security, supply arrangements and energization authority for the requested 2,100 MW development target.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL10 / 31
DOMAIN 02 · EVIDENCE AND DECISION

Natural gas

The retained analysis describes an expired gas proposal and a preliminary generation plan. Binding fuel, transportation and plant commitments remain to be established.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

The retained analysis describes the discussion-stage proposal as expired. Update it and negotiate binding supply and transportation terms with confirmed volume and credit support.

Survey and permit the lateral, and coordinate plant, EPC, OEM, emissions and fuel-balance documentation.

Proposed next output

Obtain binding fuel and transportation terms

Update the source-described expired proposal; negotiate binding fuel and transportation terms and coordinate the lateral, plant, OEM, EPC, air permit and fuel balance.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL11 / 31
DOMAIN 03 · EVIDENCE AND DECISION

Land title

The source reports a recorded deed and a 3,979.63-acre title survey. Current title matters and differing parcel scopes require reconciliation.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

land-03Confirmed

A title survey depicts a 3,979.63-acre tract and supplied record access, telephone, and water-related easements.

Analyst implications

Before closing or relying on corridors, obtain the current title commitment and Schedule B instruments; review minerals and liens; confirm that access and utility rights serve the planned facilities.

Reconcile the 3,979.63-acre survey, 4,005.86-acre Phase I scope and 4,500-acre appraisal premise in one parcel crosswalk.

Proposed next output

Complete title and parcel reconciliation

Obtain current title exceptions and mineral review; reconcile deed, survey, Phase I, appraisal, tax and KML acreage.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL12 / 31
DOMAIN 04 · EVIDENCE AND DECISION

Transmission / substation

A 10% substation package and schematic 345 kV corridor support design development. Secured rights, crossing approval and issued design remain outstanding.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Survey the route, reconcile endpoints, secure easements and I-10 crossing approval, and obtain utility acceptance before relying on the corridor design.

Complete the final one-line, protection, grounding, equipment, structure-spotting and substation-site documentation for issued design.

Proposed next output

Complete the corridor and substation design

Survey the route, secure rights and crossing approval, reconcile endpoints and complete utility-approved design.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL13 / 31
DOMAIN 05 · EVIDENCE AND DECISION

Environmental / geotech

The Phase I reports no recognized environmental conditions for its scope. Terrain screens and a contamination assessment do not complete site engineering or environmental approvals.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Investigate geotechnical and karst conditions for halls, power facilities, roads, substations and utility corridors.

Complete field wetlands and waters, parcel-specific flood and drainage, species, cultural, air and noise work as layout and permitting develop.

Proposed next output

Complete targeted field and design studies

Investigate geotechnical and karst conditions, wetlands and waters, flood and drainage, and generation-related air and noise constraints.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL14 / 31
DOMAIN 06 · EVIDENCE AND DECISION

Water

Testing and prospecting identify water-quality results and drilling targets. Sustainable yield, rights, permits and a phased campus balance remain unproven in the cited record.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Drill priority wells and complete extended pumping, drought, interference and quality tests, together with rights and permit work, to establish a reliable source.

Prepare a phase-level water and wastewater balance to size treatment, storage, redundancy, discharge and reuse infrastructure.

Proposed next output

Demonstrate the phased water supply

Drill and test priority targets, establish rights and permits, and complete the phased water and wastewater balance.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL15 / 31
DOMAIN 07 · EVIDENCE AND DECISION

Fiber

The source reports nearby backbone capacity and an optional diversity concept. Allocated, contracted and physically diverse campus service remains to be established.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Obtain written strand or wavelength allocation and service or IRU terms covering endpoints, latency, service levels, price and delivery date.

Survey the on-parcel lateral, secure its rights and demonstrate two physically diverse routes from end to end.

Proposed next output

Contract and validate resilient connectivity

Obtain allocation and commercial terms, survey and secure the lateral, validate latency and document physical diversity.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL16 / 31
DOMAIN 08 · EVIDENCE AND DECISION

Access / site plan

Recorded access and concept geometry support planning. Legal and physical access, construction logistics and an integrated master plan still require validation.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Reconcile legal and physical access; validate heavy-haul, traffic, emergency circulation and required road approvals before fixing construction logistics.

Prepare an engineered phased master plan integrating grading, drainage, stormwater, roads, halls and all utility corridors.

Proposed next output

Issue the logistics and utility master plan

Reconcile legal access; complete heavy-haul, emergency access, grading, drainage, stormwater and integrated corridor design.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL17 / 31
DOMAIN 09 · EVIDENCE AND DECISION

Equipment / procurement

Preliminary specifications and delivery schedules identify procurement needs. The cited record does not establish committed manufacturing slots or vendor availability.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

Analyst implications

Provide unredacted OEM, EPC, purchase-order, deposit, manufacturing-slot, pricing and vendor-schedule evidence to establish committed availability.

Complete the final technical, acceptance, warranty, spares, service, heavy-haul and storage plans alongside design and site readiness.

Proposed next output

Confirm equipment commitments

Provide unredacted vendor and EPC commitments, slot and payment evidence, final specifications, acceptance plans and logistics.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL18 / 31
DOMAIN 10 · RECORDED EVIDENCE

Schedule · evidence

The source schedules do not yet establish one governing delivery baseline. BTM completion, grid-study targets and the conditional PEC ramp describe different milestones.

Status labels reproduce the source record. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL19 / 31
DOMAIN 10 · IMPLICATIONS AND PROPOSED OUTPUT

Schedule · decision

The portal’s Q2 2027 owner energization target, introduced in the 16 September portal revision, is separate from the retained source milestones. A current governing baseline remains to be agreed.

Analyst implications

Reconcile the 2027 BTM milestone, April 2028 grid-study target and 2030–2032 PEC ramp in one integrated master schedule updated to current progress.

Define first power, first load, energization, substantial completion and ready for service; link each to utility, permit, fuel, procurement and commissioning conditions before communicating a delivery commitment.

Proposed next output

Establish one governing delivery schedule

Reconcile workstream dates and milestone definitions in a current baseline with dependencies, critical path and contingency.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL20 / 31
DOMAIN 11 · EVIDENCE AND DECISION

Appraisal / finance

The appraisal uses a different acreage and assumed entitlement basis. Reconcile these assumptions and the capital model before investment reliance.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

finance-02Confirmed

The appraisal assumes correct client mapping and full entitlement for heavy electric and natural-gas development and was prepared without a property inspection.

Analyst implications

Before investment reliance, reconcile the appraisal with current title acreage, entitlement, infrastructure maturity and scenario-based development costs.

Prepare the project model, sources and uses, capital stack, sponsor support, incentives, commitments and downside sensitivities for financing decisions.

Proposed next output

Reconcile valuation and capital planning

Update the valuation basis for title and infrastructure maturity; provide phased budget, capital plan, incentives, commitments and downside cases.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL21 / 31
DOMAIN 12 · EVIDENCE AND DECISION

Permitting

The record contains a limited zoning statement and planned air-permit work. The required approvals and application status need a complete register.

Recorded evidence

Status labels reproduce the source record. Preparation basis.

permit-01Confirmed

The appraisal states that the property is outside city limits and not regulated by a municipal planning or zoning authority, subject to the appraisal's limited zoning analysis.

Analyst implications

Create a complete permit register and status record for air, water, stormwater, access, environmental, fire, pipeline and utility approvals.

Advance the planned TCEQ work with the application, emissions modeling, agency correspondence, public-notice plan and issuance path.

Proposed next output

Create the permit register and confirm status

Advance priority applications, retain agency correspondence and link each approval to design and schedule conditions.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL22 / 31
KILO · EVIDENCE ANNEX

Document and analysis register

Canonical source IDs connect each claim to its recorded document pages.

D01 · LCRA load study agreement

LCRA Large Load Interconnection Study Agreement (Oct 2025).pdf

October 2025 · Original-document reference

Recorded pages 1, 15: grid-01
Recorded pages 6–8: grid-02
Recorded pages 7: tx-01
Recorded pages 14: sched-03
Page not specified: grid-m01
D02 · PEC facility-extension agreement

Blue_Fox_Development_PEC_Transmission_FEA_20260710_redacted.pdf

Effective July 10, 2026 · Original-document reference

Recorded pages 1–4: grid-03
Recorded pages 1: grid-05, sched-04
Recorded pages 4: equip-03, equip-m01
Page not specified: grid-m01, sched-m01
Recorded pages 7: grid-m02
D03 · Large-load survey

LLI-2421 Large Load Survey (rev 2).pdf

Revision 2; date not stated · Original-document reference

Recorded pages 1–2: grid-04
D04 · Dynamic-load survey

LLI-2421 ERCOT Dynamic Load Survey (rev B).pdf

Revision B; date not stated · Original-document reference

Recorded pages 1–2: sched-02
Recorded pages 4: tx-m01
Page not specified: sched-m01

Titles and pages come from retained analysis; original PDFs have not been independently reviewed. Links locate annex records; obtain current originals through controlled diligence. Alias groupings remain provisional. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL23 / 31
KILO · EVIDENCE ANNEX

Document and analysis register · 2

Canonical source IDs connect each claim to its recorded document pages.

D05 · Kinder Morgan transportation proposal

Petrolink-KMTP Kerr Proposed Term Sheet_2026.05.13.pdf

May 13, 2026 · Original-document reference

Recorded pages 1: gas-01, gas-02, gas-m01
D07 · Wild Horse Ranch deed

Wild Horse Ranch Deed (3,996 ac).pdf

Recorded May 8, 2024 · Original-document reference

Recorded pages 1, 13: land-01
Recorded pages 3, 6, 13: land-02
Recorded pages 11: access-01
Page not specified: land-m01, access-m01

Titles and pages come from retained analysis; original PDFs have not been independently reviewed. Links locate annex records; obtain current originals through controlled diligence. Alias groupings remain provisional. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL24 / 31
KILO · EVIDENCE ANNEX

Document and analysis register · 3

Canonical source IDs connect each claim to its recorded document pages.

D09 · Phase I environmental assessment

Phase I Environmental Site Assessment (Jan 2026).pdf

January 2026 · Original-document reference

Recorded pages 4: land-04, geo-01, land-m02, geo-m01, geo-m02
D10 · Preliminary substation design

Kerr Data Center 1 - 10% Substation Package.pdf

10% design; date not stated · Original-document reference

Recorded pages 1, 4–5: tx-02
Recorded pages 5: equip-01
Page not specified: tx-m02, equip-m02
D11 · Transmission and campus schematic

11) Wild_Horse_11x171.pdf

Date not stated in retained reference · Original-document reference

Recorded pages 1: tx-03, access-03, tx-m01
Page not specified: access-m02
D12 · Terrain screen: less than 10% slope

WH Buildable Area 10% Slope.pdf

Date not stated in retained reference · Original-document reference

Recorded pages 1: geo-02, access-03
Page not specified: access-m02

Titles and pages come from retained analysis; original PDFs have not been independently reviewed. Links locate annex records; obtain current originals through controlled diligence. Alias groupings remain provisional. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL25 / 31
KILO · EVIDENCE ANNEX

Document and analysis register · 4

Canonical source IDs connect each claim to its recorded document pages.

D13 · Terrain screen: less than 5% slope

WH Buildable Area 5% Slope.pdf

Date not stated in retained reference · Original-document reference

Recorded pages 1: geo-02, access-03
Page not specified: access-m02
D14 · Groundwater prospecting report

Wild Horse Ranch Seismic Survey - Final Report.pdf

March 2024 program · Original-document reference

Recorded pages 4: geo-03
Recorded pages 4–6: water-03
Recorded pages 6, 8: water-04
Recorded pages 6, 8–9, 17: water-m01
D15 · Trinity well laboratory results

HGCD Water Well Testing Results - Trinity Well.pdf

Sample taken December 18, 2025 · Original-document reference

Recorded pages 1: water-01
Recorded pages 1–2: water-02
D16 · Fiber connectivity summary

14) Kerr Summary.pdf

Date not stated in retained reference · Original-document reference

Recorded pages 1: fiber-01
Recorded pages 1–3: fiber-02
Recorded pages 3–4: fiber-03
Recorded pages 5: fiber-m01
Recorded pages 4–5: fiber-m02

Titles and pages come from retained analysis; original PDFs have not been independently reviewed. Links locate annex records; obtain current originals through controlled diligence. Alias groupings remain provisional. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL26 / 31
KILO · EVIDENCE ANNEX

Document and analysis register · 5

Canonical source IDs connect each claim to its recorded document pages.

D17 · Colliers appraisal

Colliers Appraisal - Blue Fox (Dec 2025).pdf

December 12, 2025 · Original-document reference

Recorded pages 5, 8: finance-01
Recorded pages 5, 10, 13: finance-02
Recorded pages 29: permit-01
Recorded pages 25: land-m02
Recorded pages 5, 8, 10, 13: finance-m01
D18 · Conceptual site polygons

WHR Map.kml

Date not stated in retained reference · Planning-file reference

Page not specified: access-03, access-m02

Titles and pages come from retained analysis; original PDFs have not been independently reviewed. Links locate annex records; obtain current originals through controlled diligence. Alias groupings remain provisional. Preparation basis.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL27 / 31
KILO · EVIDENCE ANNEX

How to read the source types

Each source type answers a different question. Treat source classification and project completion separately.

Analysis and preparation

Authored analysis

39 claims, 24 analyst notes and 12 proposed actions retained from StrataIQ’s source analysis.

Underlying source register

Separate document and claim records; differences from the authored analysis require reconciliation.

Historical score snapshot

September 2, 2026 stored values; method, weights and change explanation are not established.

Preparation record

The preparation record keeps documentary references, analyst text, counts and scores separate.

Other retained records

Ascendant preliminary schedule

A 191-engine / 477.5 MW schedule; its relationship to the authored Phase 1 plan is unresolved.

Separate gas commercial summary

Separate Oasis proposed terms and a nonbinding generation inference; binding fuel is not established.

Descriptive evidence assessment

17 covered, 30 partial and 12 not found. Counts differ from claims and from readiness scores.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL28 / 31
KILO · EVIDENCE ANNEX

Terms used in this annex

Technical abbreviations and named organizations used in the evidence record.

Project and commercial terms

VDR
Virtual data room
BTM
Behind-the-meter generation
POI
Point of interconnection
FEA
Facility Extension Agreement
IRU
Indefeasible right of use
OEM
Original equipment manufacturer
EPC
Engineering, procurement and construction

Organizations and source terms

LCRA
Lower Colorado River Authority
PEC
Pedernales Electric Cooperative
ERCOT
Electric Reliability Council of Texas
TCEQ
Texas Commission on Environmental Quality
REC
Recognized environmental condition
KML
Keyhole Markup Language; geospatial file format

Historical filenames and named counterparties are preserved. Publisher branding does not change the parties to a deed, proposal or agreement.

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL29 / 31
KILO · EVIDENCE ANNEX

Historical platform values · September 2, 2026

Reference data only. No current readiness conclusion is derived from these values.

Stored fieldValue
Overall85
Stored bandViable
Previous stored score52
Stored change+33
Power & interconnection90
Water & cooling70
Natural gas90
Fiber & connectivity90
Land & buildability75
ERCOT / regulatory60
Financial / valuation90

Interpretation limit

These September 2, 2026 platform values are historical source data. They do not establish current readiness, an independent rating or a market rank.

The materials do not establish a usable scoring method, category weights, thresholds or explanation for the change from 52 to 85. The +33 value must not be interpreted as measured project progress.

Unreconciled source bases

The separate finance display is 50 and includes an appraisal-not-found note; the authored analysis cites an appraisal. The descriptive counts of 17 covered, 30 partial and 12 not found use another basis.

Resolve the scoring method and source differences before using a readiness score. Finance reconciliation · Descriptive matrix

KILO · EVIDENCE ANNEXContentsHYPERBASE · CONFIDENTIAL30 / 31
KILO · EVIDENCE ANNEX

Agree the next diligence scope

The proposed next step is a phased tenant brief and a defined evidence review.

Proposed sequence

  1. Define the phased load, resilience, cooling, network and commissioning requirements.
  2. Obtain controlled access to current source documents and reconcile the document register.
  3. Test the tenant brief against utility studies, fuel and service terms, permits, rights and the governing schedule.
  4. Use the resulting evidence to define the scope and conditions for definitive agreements.

Outputs to agree

A tenant design basis, a prioritized diligence register, document access and review responsibilities, and decision criteria for the next commercial discussion.

Owners, dates, scope, fees and commercial terms are to be agreed. This proposed sequence is not a notice to proceed or a commitment of capacity, price or delivery.

Publication basis

HyperBase for Ascendant LLC · KILO Evidence Annex · Rev 3.2 · September 16, 2026.

Prepared from the retained analysis snapshot of September 15, 2026. Source-document dates and historical platform dates retain their own meaning. Commercial reliance should be governed by current originals and applicable definitive agreements.